Excavations over 1.5m Baseline Safety Standards

Excavations over 1.5m

Minimum Requirements
Permit
Excavation Permit
Competencies
LE Excavator Licence Construction HSE Induction
Risk Management
Risk Assessment (Register) SWMS High Risk Workshop Emergency Rescue Plan
PPE Mandatory
PPE Additional

Excavation work can be defined as work to make an excavation or to fill or partly fill an excavation. This includes the removal of soil or rock from a site form an open face, hole or cavity, including trenches, shafts and tunnels.

Context

Excavation work involves managing a range of hazards, including excavation collapse, the risks of working near mobile plant and falling into trenches. If uncontrolled, these hazards can lead to injuries or fatalities to workers as a result of becoming entrapped in excavation, struck by mobile plant or falling into trenches or holes.

High risk construction work relating to excavation is that which is carried out in or near:

  • A shaft or trench with an excavated depth of greater than 1.5 metres

  • or 150mm of digging/ penetration, or A tunnel.

Process
Step 1 Pre-construction planning

The risks arising from excavation are to be identified, assessed and controlled in the Project Risk Register, in accordance with the hierarchy of controls.

A high risk workshop MUST be undertaken to identify all known and potential risks associated with excavations over 1.5m

In the planning stages and prior to commencing work, the Baseline site representative shall ensure the following activities have been considered:

  • A structural or Geotechnical Engineer must assess adjacent structures / materials / foundations and identify controls

  • All overhead and underground services have been identified and managed, including liaison with asset owners

  • Identification of underground services must include Dial Before You Dig conducted at least three days prior to commencement, and may include ground penetrating radar or potholing

  • A dig plan, methodolgy or SWMS is developed detailing the nature of works to be undertaken and the method used to prevent ground collapse

Step 2 Contractor requirements

All contractors must identify any High Risk activity within their scope of work, evidence of experience carrying out this activity, provision for full time supervision, relevant licenses and competencies of supervisor and workers to undertake excavation activities over 1.5m

All contractors are required to develop and submit, a specific safe system of work, e.g. SWMS, for this High Risk activity to the Baseline site representative for approval (7days) prior to commencing works

This MUST include an Emergency Procedure / Rescue Plan, evidence that supervisors and workers are trained in the procedure

Note: The Baseline expectation is that our contractors will follow all safety requirements listed within our standards

Step 3 Pre-activity review

Proposed methodology to be reviewed by Project Team and assess for need to conduct activity specific High Risk Workshop.

(If required) High Risk Workshop to be conducted with contractor undertaking activity and Baseline Project Team.

Methodology, competencies and timing MUST be confirmed and agreed with all stakeholders

Identify if excavation will be considered a Confined Space

Note: If shoring systems are to be utilised, they must be designed by a Geotechnical or Structural Engineer in a shoring plan, and MUST be installed by a competent tradesperson - Refer to competencies at end of controls section

Step 4 Work activity approval

An Excavation Permit must be submitted to and approved by the Baseline site manager/supervisor prior to start work, and can be valid for seven consecutive days at a time, with the condition of daily control reviews.

The permit, in line with approved SWMS, must address the following:

  • Adequate barriers and signage around excavation work

  • How potential falls into the excavation will be controlled in accordance with HRS – Working at Heights

  • How vehicle or mobile plant movements around the excavation will be controlled (including a Vehicle Management Plan if required).

  • Emergency procedure shall be established specific to the excavation works being conducted.

  • Confined space risk has been addressed if applicable

Step 5 Work activity monitoring

Baseline site manager / supervisor MUST monitor the excavation activity (from outside the excavation exclusion zone) until the work activity has been completed.

Weather condition's MUST be monitored for the duration of works

Excavated material placement MUST be monitored to confirm distance from edge of trench

A Task Observation should be conducted by a Baseline Project Team member to record the works being carried out as per approved SWMS.

The Subcontractor Supervisor MUST be present at all times to ensure the excavation permit and SWMS are being adhered to and excavation entry is prevented at end of each shift

The Subcontractor Supervisor MUST inspect the excavation at the start of each shift and confirm safe to enter

Step 6 Completion of work activity

At the end of the activity the Civils contractor supervisor MUST confirm the excavation has been vacated by all team members and has been closed off to prevent unauthorised entry and can complete backfill.

The Baseline site manager / supervisor MUST confirm the area has been made safe and close out the excavation permit

Controls
Elimination Physically remove the hazard

Work should be undertaken above ground where possible, to eliminate the need for tunnels or shafts.

Substitution Replace the hazard

Mobile plant shall be used instead of manual labour to conduct excavation works where possible

Schedule works to occur outside of high-traffic hours or staggered to reduce mobile plant interactions

Isolation Isolate people from the hazard

All overhead and underground services in the vicinity of the excavation shall be identified and controlled through the use of isolations, or safe approach distances.

No spoils, plant or equipment shall be stored in the ‘zone of influence’ of an excavation at any time, unless a ground support system has been designed and installed to carry such loads by a Geotechnical Engineer.

Engineering Replace the hazard

Safe access and egress must be provided at all times for workers entering excavations

  • Excavations shall be stabilised through the use of benching, battering or shoring systems when greater than 1.5m in depth

  • Controls shall be to implemented to prevent falls into excavations, including flagging, barricades or signage

  • Plant safety devices shall be verified as operational before commencing works.

  • Earth protection is to be provided on all mobile plant and directional drills

Administration Change the way people work

An Excavation Permit must be approved prior to commencing any excavation works

  • As part of recurring Site Inspections, Excavations shall be routinely inspected by competent persons

  • Dial Before You Dig (DBYD) and service locations shall be conducted before commencing any excavation work. Identified services shall be marked on the ground and safe approach distances observed as per the Excavation Permit

  • Plant operators must be qualified or competent via VOCs

  • Spotters are to be used for all excavation activities

  • Excavation areas shall be sampled for hazardous materials before commencing works

PPE Protect the worker with PPE

Hard hats are to be mandatory around operating plant and while inside an excavation greater than 1.5m

Additional PPE MUST be considered in relation to known uncontrolled risk

Notes

Clearance distances from from underground services and assets using hand dig and mechanical excavating methods

Asset

Hand Tools

Machinery NO-GO

Low and Medium Pressure gas service

N/A

300mm

Low and Medium-Pressure mains

N/A

300mm

High-Pressure Gas Service, Main or Pipeline

300mm with asset owner supervision

1000mm

Low-Voltage Electrical Cable (>1kV)

Close proximity

300mm

Electricity Conductor (11kV – 33kV)

Close proximity

600mm

Extra High-Voltage Cable (132kV – 330kV)

Contact asset owner

Contact asset owner

Underground sub-transmission cable (>132kV)

Contact asset owner

Contact asset owner

Telecommunications cables

Contact asset owner

Contact asset owner

Water pipelines

N/A

300mm

Sewerage pipelines

N/A

300mm

High-Voltage Electrical Cable (1kV – 33kV)

Close proximity

Contact asset owner

Shoring Inspection and Competency

Activity

Competency

Record

Installation and removal of shoring

RIICCM210E - Install trench support or equivalent

Handover certificate

Pre-use inspection, immediately after installation

Structural or geotechnical engineer

Handover/Inspection certificate

Daily pre-use inspections

N/A

Permit Control Verification Checklist

Inspection prior to removal

RIICCM210E - Install trench support or equivalent

Inspection certificate

Thank you for your enquiry.
First Name:
Last Name:
Email:
Mobile:
Location:
CV: