Scaffold Baseline Safety Standards

Scaffold

Minimum Requirements
Permit
Work at Heights (1m rule not possible)
Competencies
Basic Scaffold (SB) Intermediate Scaffold (SI) Advanced Scaffold (SA) Construction HSE Induction
Risk Management
Project Risk Register Engineer Approved design SWMS Rescue Plan
PPE Mandatory
PPE Additional

A scaffold is a temporary structure erected to support access or working platforms, this includes the individual components of plant

Context

A scaffold is a temporary structure erected to support access or working platforms. Scaffolding refers to the individual components of a scaffold, such as standards, transoms and ledgers.

Baseline often uses scaffolds to establish safe, stable working platforms, access and egress and edge protection for roofs and other work areas where workers cannot undertake works from the ground or finished floor.

The risks associated with scaffolds include falls from heights, falling objects, manual handling and temporary structure collapse, which may impact both scaffolders undertaking scaffold work, workers using the structure or workers and other people in the vicinity of the scaffold.

These include: working near energised overhead electric lines / mobile plant and traffic / fixed plant / mixing scaffold components / falls from height / falling objects / scaffold collapse / unauthorised access / use or alteration / ground conditions / hazardous manual tasks

Process
Step 1 Pre-construction planning

The nominated project manager must arrange a pre-construction risk review meeting with the project team to identify all known and potential risks relating to scaffolding including access.

The risks arising from scaffolds are to be identified, assessed and controlled in the Project Risk Register, in accordance with the hierarchy of controls.

The Baseline Scaffold Design Brief meeting type MUST be conducted to identify all scaffold requirements

Note: Industry best practice 1m erection methodology MUST be followed, unless not possible, task specific SWMS MUST be provided and approved

Step 2 Contractor requirements

All contractors must identify any High Risk activity within their scope of work, evidence of experience carrying out this activity, provision for full time supervision, relevant licenses and competencies of supervisor and workers

All contractors are required to develop and submit, a specific safe system of work, e.g. SWMS, for this High Risk activity to the Baseline site representative for approval (7days) prior to commencing works

This MUST include an Emergency Procedure / Rescue Plan, evidence that supervisors and workers are trained in the procedure

The Baseline expectation is that our contractors will follow all safety requirements listed within our standards

Scaffolds must conform to the following minimum requirements and relevant legislation, codes of practice and Australian standards:

− It is designed by an appropriately qualified scaffolder (refer to Scaffold Licencing) and endorsed by a an appropriately qualified engineer, who will also review and approve any design variations

− The plan includes a site layout, engineer approved drawings for scaffold

− Includes documented design parameters provided by the scaffold manufacturer.

− Includes any considerations raised in the Scaffold Design Brief meeting

− Include a structural and/or geotechnical assessment

Step 3 Pre-activity review

Proposed methodology to be reviewed by Project Team and assess for need to conduct activity specific High Risk Workshop.

1m erection methodology MUST be followed, unless not possible, task specific SWMS MUST be provided and approved and High Risk Workshop to be conducted with contractor undertaking activity and Baseline Project Team.

Methodology, competencies and timing MUST be confirmed and agreed with all stakeholders

Any considerations raised in the Scaffold Design Brief meeting − Include a structural and/or geotechnical assessment of building structures, materials or foundations and their results.

Confirmation scaffold structure is designed by an appropriately qualified scaffolder (refer to Scaffold Licencing) and endorsed by a an appropriately qualified engineer

Step 4 Work activity approval

Prior to commencing scaffold erection/dismantle and where the work cannot conform to the 1m rule a Work at Heights Permit MUST be submitted by the subcontractor supervisor and approved by the Baseline site manager.

Where 1m rule cannot be followed, a task specific toolbox talk MUST be conducted by a Baseline Project Team member immediately prior to commencing works, and include all workers involved in the activity and detail the rescue plan

Note: Work at Heights Permit will be required where a harness must be worn

Step 5 Work activity monitoring

Baseline site manager / supervisor MUST monitor the scaffold erection activity until the work activity has been completed.

A Task Observation should be conducted by a Baseline Project Team member to record the works being carried out as per approved SWMS.

The Subcontractor Supervisor MUST be present at all times to ensure the permit (where required) is being adhered to and rescue plan can be activated

Step 6 Completion of work activity

At the end of the activity the subcontractor scaffold supervisor MUST conduct a scaffold inspection with the Baseline site manager to confirm the scaffold had been erected in accordance with approved engineer endorsed design and provide a scaffold handover certificate to confirm.

A scafftag MUST be placed at all scaffold access points and scaffold re-inspected every 30 days or as per Australian standard

Any Work at Height Permits MUST be closed out

Controls
Elimination Physically remove the hazard

Where possible works are to be conducted from ground level, e.g. fabricating items on the ground prior to installation at heights

Substitution Replace the hazard

A less hazardous form of scaffolding or access system (based on the requirements of its use i.e., resistance, weight load, occupancy load etc) is to be selected.

Isolation Isolate people from the hazard

Exclusion zones must be established around scaffold works (e.g., during erection, modification and dismantling) to protect other works from potential object fall from height hazards.

  • Scaffold adjacent to mobile plant operating areas or traffic corridors must be protected by physical barriers, such as concrete barriers or water filled barriers

  • Scaffold decks must remain in place for every (2m-3m) lift and guardrails in place during scaffold installation, modification and dismantle

  • Access to incomplete scaffolding is not permitted. Physical barriers shall be installed and signposted detailing “Incomplete Scaffolding – DO NOT USE” where access to incomplete scaffold is present. Only scaffolders can access incomplete scaffold until the scaffold has been inspected and certified

  • Scaffolds shall have the means of preventing materials falling over toe boards such as chainmesh, shade cloth or brick guards

Engineering Replace the hazard

Scaffolds are to be designed in accordance with the relevant Australian standards by an appropriately qualified scaffolder (refer Scaffold Licencing), and where required, the drawings endorsed by a qualified structural engineer

  • Safe access and egress to work areas is to be maintained at all times

  • Use mechanical aids like cranes, hoists, pallet jacks or trolleys to move equipment and materials wherever possible instead of manually lifting scaffolding

  • Where there is a risk of scaffolding material or tools falling outside of an established exclusion zone, all tools and scaffolding materials must be tethered or made secure from falling

  • Encapsulation to be in accordance with AS1576: Safe use of encapsulation on scaffolding

  • All anchor and tie connections shall have a proprietary anti-tamper device fitted to prevent unauthorised alterations

Administration Change the way people work

Persons erecting, altering or dismantling scaffolds MUST be appropriately licenced

  • Unauthorised alterations to scaffold will result in immediate removal from site

  • Where scaffold work requires the use of a harness to be worn a work at heights permit to be approved prior to commencing works above 2m with rescue plan in place

  • Ground and weather conditions are to be assessed by the site manager prior to working at heights for potential impacts to stability of scaffolds

  • In accordance with the Inspection, Test and Maintenance Schedule, scaffolds are to be regularly inspected to monitor the effectiveness of the structure

  • Overhead hazards are to be identified and controls implemented prior to commencing works e.g., safe approach distances for powerlines

  • A certificate of Plant Design Registration for prefabricated scaffolding must be obtained prior to erection

  • Engage the services of a competent person such as a geotechnical engineer, to assess the ground and specify suitable loading requirements

PPE Protect the worker with PPE

Harnesses should be utilised as a control measure only where the process for erection and dismantling only when the 1m rule cannot be followed

National High-Risk Work Licenses

Advanced scaffolding (SA)

Intermediate Scaffold (SI)

Basic scaffolding (SB)

All intermediate scaffolding work plus scaffolding connected with the use and operation of:

All basic scaffolding work plus scaffolding connected with the use and operation of:

Modular or prefabricated scaffolds

Cantilevered hoists

Cantilevered crane loading platforms

Cantilevered materials hoists with a maximum working load of 500 kg

Hung scaffolds, including scaffolds hanging from tubes, wire ropes or chains

Cantilevered and spurred scaffolds

Ropes and gin wheels

Suspended scaffolds

Barrow ramps and sloping platforms

Safety nets and static lines, and

Perimeter safety screens and shutters

Bracket scaffolds (tank and formwork)

Mast climbers

Tube and coupler scaffolds (including tube and coupler covered ways and gantries)

Thank you for your enquiry.
First Name:
Last Name:
Email:
Mobile:
Location:
CV: